Click here for a key to the symbols used. An explanation of acronyms may be found at the bottom of the page.
From Route 1 near Castroville to Route 101 near Prunedale.
This segment is unchanged from its 1963 definition.
In 1964, a new freeway alignment of Route 1 in Castroville was adopted
that included a new junction with Route 156. This new alignment included
Route 156 being routed over a new overpass of the Southern Pacific
Railroad in Castroville. At some point between 1979 and 1981 Route 1 was
relocated west of Castroville onto a bypass. The realignment of Route 1
extended Route 156 west onto the Castroville Freeway grade to its present
west terminus.
(Source: Gribblenation Blog: "California State Route 156")
The route adoption of a new freeway routing (see below) for this segment
of Route 156 notes the following regarding the history of the route:
(Source: June 2021 CTC Agenda, Agenda Item
2.3a.(2))
Route 156 is part of the California Freeway and Expressway System in its entirety. The California Highway Commission adopted a Route 156 freeway alignment from Route 1 to 0.8 mile north of Castroville on February 19, 1957 and from 0.1 mile west of the October 25, 1961 adopted Route 183 alignment to the adopted US 101 alignment on June 22, 1996. On September 18, 1975, the California Highway Commission rescinded a portion of the 1957 and 1966 freeway adoptions between 0.2 mile east of adopted Route 183 and adopted US 101 due to monetary and other constraints leading to the unconstructed adopted route to remain unconstructed. The following reasons were stated in the Route Inventory Report dated May 1, 1975: (1) financial constraints make the feasibility of construction in the adopted corridor questionable; (2) the Regional Transportation Plan indicates widening of the existing highway will meet traffic needs; (3) the existing facility can be widened to four lanes within the existing right-of-way. Since the 1975 rescission, Route 156 and its surrounding communities have changed. New studies for the corridor started in 1997 to document the need for new transportation improvements. A Project Study Report (PSR) completed in 1998 evaluated widening Route 156 from 2-lane conventional highway to a 4-lane expressway without addressing the interchange at US 101 and SR 156. This PSR did not consider constructing an interchange at Castroville Boulevard.
The project remained inactive due to funding constraints until 2003. A Supplemental Project Study Report – Project Development Support (PSR-PDS) document was completed in April 2006 to document the change in scope. The scope of the project changed to include a reconstruction of the US 101/Route 156 interchange and construction of the Castroville Boulevard and Cathedral Oak Road interchanges along Route 156. The PSR-PDS document superseded the two PSRs from 1997 and 1998. In 2006, TAMC and the Department started the project studies for the Route 156 West Corridor Project (Project). An open house scoping meeting was held on November 15, 2006 in Castroville. On July 20, 2009, the Department held a public hearing in Castroville to present the different alternatives studied in the approved draft environmental document. On January 31, 2013, the Department completed project studies and a FEIR/Environmental Assessment (Environmental Document) leading to a Finding of No Significant Impact. The PR was approved on January 31, 2013, recommending the construction of a new freeway alignment south of the existing alignment. The Commission accepted the Environmental Document and approved the project for future consideration of funding on August 6, 2013 with Resolution E-13-65. A revalidation under the National Environmental Policy Act was approved on October 8, 2020. A Supplemental PR was approved on May 18, 2021 to modify the Project’s construction phasing to construct the Castroville Boulevard interchange first, now referred to as Segment 1. Segments 2 and 3 will complete the construction of the four-lane freeway from the new Castroville Boulevard interchange to the junction of US 101 and Route 156.
Existing Route 156 functions as a rural two-lane undivided highway with 12-foot lanes and 8-foot shoulders. It has no passing lanes but includes left turn pockets at intersections to improve operations. Left-turn and right-turn movements on Route 156 at the intersections between Castroville Boulevard and the junction of Route 156 and US 101 result in a higher than average rate of collisions statewide. The proposed Route 156 freeway will include the construction of a new interchange to improve local and interregional traffic circulation. The purpose of the project is to improve safety, operation, and local and interregional traffic circulation. The Project will construct a four-lane freeway on a new alignment. The existing Route 156 will be converted to local frontage road. A new interchange will be constructed near the existing intersection of Route 156 and Castroville Boulevard to address traffic demand and improve safety along Route 156 in Monterey County. Improvements will be made to the connections at Route 156 and US 101. Due to funding constraints, the new interchange near Castroville Boulevard will be constructed first and other improvements will be constructed in subsequent phases. The County provided a resolution supporting the route adoption on May 18, 2021.
This entire routing was LRN 22. This segment was defined in 1933. It was not part of the original 1934 state signage of routes. It was likely signed in 1938 with the portion of Route 156 E of US 101, but it doesn't show up on state highway maps until after 1964.
Originally Route 1/LRN 56 northbound entered Castroville via Preston Road
where it turned left at Merritt Street. Route 156/LRN 22 westbound entered
Castroville by way of an at-grade crossing of the Southern Pacific
Railroad from Castroville Boulevard onto Salinas Street. Route 156/LRN 22
made a right had turn on Merritt Street and met Route 1/LRN 56 at Preston
Road. Route 183/LRN 118 northbound entered Castroville on Merritt Street
and terminated at Route 156/LRN 22 at Salinas Street. The original
alignment of LRN 22 in Castroville can be seen on modern Castroville
Boulevard headed westbound towards Route 156. As Castroville Boulevard
swings left towards modern Route 156 the abandoned highway can be seen
ahead approaching the Union Pacific Railroad tracks. Route 156 would have
originally crossed the tracks at an at-grade crossing onto Salinas Street
in Castroville. A pedestrian overpass now exists where the at-grade
highway crossing once existed. LRN 22 would have originally headed
westbound on Salinas Street to Merritt Street. Originally LRN 22 and
possibly Route 156 turned northward towards downtown Castroville and Route 1 before 1944. After 1944 Route 156 (the highway shows up topographical
maps from an undetermined date) terminated at Merritt Street where it meet
Route 1 which would have come in from the opposite direction on Salinas
Street. Southbound Merritt Street was LRN 118 which became Route 183
during the 1964 Highway Renumbering.
(Source: Gribblenation Blog: Historic Highway Alignments in Castroville (CA 1, CA 156 and CA 183))
Constructed to freeway standards from Route 1 near Castroville to Castroville Blvd.
Until the early 1980s, Route 1 entered Castroville from the south via Route 156 eastbound (the current freeway), then exited at the diamond interchange for Merritt Street (~ MON R1.096) and continued northwest via Merritt. However, by the mid-1980s, the current Castroville bypass was constructed; as a consequence, the portion of freeway on Route 1 between Merritt Street and the bypass became an extension of Route 156, and Merritt Street became part of Route 183.
Castroville/Prunedale West Corridor (MON R1.3/T5.2)
The SAFETEA-LU act, enacted in August 2005 as the
reauthorization of TEA-21, provided the following expenditures on or near
this route:
In May 2013, the Transportation Agency for Monterey
County released a report that indicated converting the outdated two-lane
Route 156 into a nearby four-lane toll road between Route 1 and US 101
could be mostly paid for by modest tolls, ranging from $1.60 to $2.50 a
trip. That would cover most of the $268 million in construction costs and
other safety improvements along the Route 156 corridor. And most of the
improvements could be completed in less than a decade, compared with the
current 30-year-plus time frame.
(Source: Mercury News, 5/20/13)
In August 2013, the CTC approved for future consideration of funding a project that will widen a portion of Route 156 from two lanes to four lanes and convert a portion of US 101 from an expressway to a freeway near the city of Castroville. The project is not fully funded. Design and Right of Way are programmed in the 2012 State Transportation Improvement Program. The total estimated cost is $104,194,000 for capital and support. Construction is estimated to begin in Fiscal Year 2018-19 or later. The scope, as described for the preferred alternative, is consistent with the project scope programmed by the Commission in the 2012 State Transportation Improvement Program. The project would add two new lanes in both EB and WB directions S of the existing Route 156 (which will impact farmland), on a new alignment.
The 2018 STIP, approved at the CTC March 2018 meeting, appears to deallocate $21,400K from PPNO 0057C and recast it as the Route 156 West Corridor (allocating $1,600K), In and near Prunedale and Castroville, from 0.6 mile west of Castroville Boulevard to the Route 101/156 separation. Widen to 4 lane divided expressway. 05-Mon-156 R1.3/T5.2 05-Mon-101 94.6/96.8.
In March 2020, the CTC approved the 2020 STIP, which
continued programmed funding of $1,600K for PPNO 0057C "Rt 156 West
Corridor". It also included PPNO 057C, 4-lane expressway,
Castroville-Prunedale, in the Interregional portion of the STIP with no
change in programming: $7.700K in prior year funding.
(Source: March 2020 CTC Agenda, Item 4.7, 2020 STIP
Adopted 3/25/2020)
In June 2021, the CTC adopted a freeway routing for
this corridor: Route 156 from Route 183 to US 101 as a new freeway
alignment as part of the Route 156 West Corridor Project that will
construct a new freeway alignment with interchanges south of the existing
Route 156 alignment. The Department approved the Project Report (PR)
on January 31, 2013, and the Commission approved the Resolution for the
Future Consideration of Funding for Final Environmental Impact Report
(FEIR) via Resolution E-13-65 on August 6, 2013. A revalidation
form, as an update to the environmental document, and a Supplemental PR
were signed on October 8, 2020 and May 18, 2021, respectively.
(Source: June 2021 CTC Agenda, Agenda Item
2.3a.(2))
The adoption resolution notes:
(Source: June 2021 CTC Agenda, Agenda Item
2.3a.(2))
Route 156 is part of the California Freeway and Expressway System in its entirety. The California Highway Commission adopted a Route 156 freeway alignment from Route 1 to 0.8 mile north of Castroville on February 19, 1957 and from 0.1 mile west of the October 25, 1961 adopted Route 183 alignment to the adopted US 101 alignment on June 22, 1996. On September 18, 1975, the California Highway Commission rescinded a portion of the 1957 and 1966 freeway adoptions between 0.2 mile east of adopted Route 183 and adopted US 101 due to monetary and other constraints leading to the unconstructed adopted route to remain unconstructed. The following reasons were stated in the Route Inventory Report dated May 1, 1975: (1) financial constraints make the feasibility of construction in the adopted corridor questionable; (2) the Regional Transportation Plan indicates widening of the existing highway will meet traffic needs; (3) the existing facility can be widened to four lanes within the existing right-of-way. Since the 1975 rescission, Route 156 and its surrounding communities have changed. New studies for the corridor started in 1997 to document the need for new transportation improvements. A Project Study Report (PSR) completed in 1998 evaluated widening Route 156 from 2-lane conventional highway to a 4-lane expressway without addressing the interchange at US 101 and SR 156. This PSR did not consider constructing an interchange at Castroville Boulevard.
The project remained inactive due to funding constraints until 2003. A
Supplemental Project Study Report – Project Development Support
(PSR-PDS) document was completed in April 2006 to document the change in
scope. The scope of the project changed to include a reconstruction
of the US 101/Route 156 interchange and construction of the Castroville
Boulevard and Cathedral Oak Road interchanges along Route 156. The
PSR-PDS document superseded the two PSRs from 1997 and 1998. In 2006, TAMC
and the Department started the project studies for the Route 156 West
Corridor Project (Project). An open house scoping meeting was held
on November 15, 2006 in Castroville. On July 20, 2009, the
Department held a public hearing in Castroville to present the different
alternatives studied in the approved draft environmental document. On
January 31, 2013, the Department completed project studies and a
FEIR/Environmental Assessment (Environmental Document) leading to a
Finding of No Significant Impact. The PR was approved on January 31,
2013, recommending the construction of a new freeway alignment south of
the existing alignment. The Commission accepted the Environmental
Document and approved the project for future consideration of funding on
August 6, 2013 with Resolution E-13-65. A revalidation under the
National Environmental Policy Act was approved on October 8, 2020. A
Supplemental PR was approved on May 18, 2021 to modify the Project’s
construction phasing to construct the Castroville Boulevard interchange
first, now referred to as Segment 1. Segments 2 and 3 will complete
the construction of the four-lane freeway from the new Castroville
Boulevard interchange to the junction of US 101 and Route 156.
Existing Route 156 functions as a rural two-lane undivided highway with 12-foot lanes and 8-foot shoulders. It has no passing lanes but includes left turn pockets at intersections to improve operations. Left-turn and right-turn movements on Route 156 at the intersections between Castroville Boulevard and the junction of Route 156 and US 101 result in a higher than average rate of collisions statewide. The proposed Route 156 freeway will include the construction of a new interchange to improve local and interregional traffic circulation. The purpose of the project is to improve safety, operation, and local and interregional traffic circulation. The Project will construct a four-lane freeway on a new alignment. The existing Route 156 will be converted to local frontage road. A new interchange will be constructed near the existing intersection of Route 156 and Castroville Boulevard to address traffic demand and improve safety along Route 156 in Monterey County. Improvements will be made to the connections at Route 156 and US 101. Due to funding constraints, the new interchange near Castroville Boulevard will be constructed first and other improvements will be constructed in subsequent phases. The County provided a resolution supporting the route adoption on May 18, 2021.
The existing Route 156 will be relinquished to Monterey County as a superseded-by-relocation relinquishment once the freeway construction is completed. Relinquishment agreements will be executed after the freeway route adoption is approved. The total project cost for the Castroville Boulevard Interchange Project (Segment 1) is $35,991,000, including right-of-way capital cost. The project is funded in 2021-2022 utilizing funds from Monterey County’s Transportation Safety and Investment Plan (Measure X), Trade Corridor Enhancement Program, Statewide Transportation Improvement Program – Regional Improvement Program, and other local funds. The estimated project costs for Segment 2 and Segment 3 are $106,225,000 and $250,890,000, respectively. A superseding Freeway Agreement will be executed by the Department after the Commission’s approval of the freeway route adoption.
Castroville Overhead (№ 44-0033L) Widening (05-Mon-156 R1.4/R2.0)
In May 2021, the CTC approved the following
construction phase SHOPP allocation(s): #8. $7,633,000. 05-Mon-156
R1.4/R2.0. PPNO 05-0900A; ProjID 0513000028; EA 0A090. Route 156 Near
Castroville, from Route 183 to Castroville Boulevard at Bridge №
44-0033L. Outcome/Output: Upgrade bridge railing and widen
bridge. Programmed allocation: $1,800,000 (Con Eng); $6,600,000 (Const).
Difference is due to preliminary engineering savings
(budgeted⇢expended): PA&ED $70,000⇢$4,146; PS&E
$2,880,000⇢$2,515,150; R/W Sup $198,000⇢$136,446.
(Source: May 2021 CTC Agenda, Agenda Item 2.5b.(1)
#8)
In December 2021, the CTC approved a request for an
additional $1,374,000 in Construction Capital for the SHOPP Bridge
Rehabilitation project on Route 156 in Monterey County to award the
construction contract. In March 2014, the project was programmed for
$4,500,000 in construction capital in the SHOPP for delivery in Fiscal
Year 2020-21. In May 2021, the project was allocated for $5,633,000
in construction capital and $2,000,000 in construction support. At
bid opening in September 2021, the amount required to award to the lowest
bidder exceeded the amount available from project allocated and G-12
funds. The Department is requesting supplemental funds in the amount
of $1,374,000 to award the construction contract.A SHOPP Amendment was
approved in May 2017 that moved the delivery year from 2017-18 to
2019-20. The construction capital was increased to $5,050,000 and
construction support was increased to $1,340,000 in construction
support. In May 2019, another SHOPP Amendment was approved to move
the delivery year from 2019-20 to 2020-21. The construction capital
was increased to $6,600,000 and construction support was increased to
$1,800,000. Caltrans had anticipated cost increases due to the complex
work site with high traffic volumes on a narrow roadway and a volatile
price environment. The project also involves coordination with the
Union Pacific Railroad. In August 2021, the Department advertised the
project and held Bid Opening in September 2021. The project received
six bids. When the bids were opened and the bid summary was
released, the low bid was 28.9 percent above the Engineer’s Estimate
(EE). The Department anticipated that the bids would come in at or
slightly above, however, the bids came in much higher than
anticipated. The primary factors leading to the increased prices
include more complex methods of construction, higher overhead costs, more
conservative price based on uncertainty of non-visible conditions, low
economy of scale, low production rates, higher design criteria of shoring,
complex staging, and higher than anticipated bid prices. Some of the
major cost increases to the bridge work were Structural Concrete (Bridge)
which was double, Bridge Removal (Portion) which was triple, and
Structures Excavation (Bridge) which was double.
(Source: December 2021 CTC Agenda, Agenda Item
2.5e.(4))
Route 156 West Corridor/Castroville Blvd Interchange (05-Mon-101, PM 94.6/96.8 05-Mon-156, PM R1.6/T5.2)
The 2018 STIP, approved at the CTC March 2018 meeting, appears to allocate $19,800K for
the Castroville Blvd Interchange (~ MON R1.819). The Monterey COG
described the project as build a new interchange at Castroville Boulevard
and Route 156, with connections to Blackie Road to improve access for
commercial traffic. There is a related project, also funded in the STIP,
that extends Blackie Road to connect to a new interchange at Route 156 and
Castroville Boulevard. The COG notes that Route 156 at Castroville
Boulevard is the top collision location in Monterey County. In addition,
Route 156 is the major link connecting the San Francisco Bay area and
North Monterey County to the Monterey Peninsula. With its present narrow
configuration, it currently operates over capacity, with substantial
delays and safety concerns, particularly during special events on the
Monterey Peninsula. This congestion affects travel to and from the
Peninsula as well as travel between US 101 and Route 1 for local
residents. In addition, the traffic impedes access to the Oak Hills
neighborhood. This project will direct truck traffic away from Merritt
Street in Castroville and from the accident‐ridden Route 183/Route 156 interchange. It will also help relieve traffic congestion on Route 156
while improving safety and local traffic circulation in North Monterey
County. The extension of Blackie Road provides traffic congestion relief
and improves safety for Oak Hills and other local communities.
In April 2018, it was reported that a new interchange
is being pursued at Castroville Boulevard and Route 156, where there is
currently a stop light. An interchange would end t-bone accidents,
rear-end collisions and make it safer by getting trucks out of
Castroville, with a new Route 156 connection to Blackie Road. This could
take five years.
(Source: Mercury News, 4/5/2018)
In March 2020, the CTC approved the 2020 STIP, which
adjusted the programmed funding for PPNO 0057D "Castroville Blvd
Interchange", from $19,800K to $27,675K.
(Source: March 2020 CTC Agenda, Item 4.7, 2020 STIP
Adopted 3/25/2020)
In June 2020, the CTC approved the following
allocation: $18,100,000 for the Right of Way capital phase for 05-Mon-156
R1.6/1.4 PPNO 05-0057D ProjID 0518000120 EA 31601 Castroville
Boulevard Interchange. Route 156 in Monterey County at Castroville
Boulevard from Post Mile R1.6 to 1.4. Build a new interchange at
Castroville Boulevard and Route 156. The project scope requires the
acquisition of 15 parcels and extensive offsite environmental
mitigation and utilities. The signalized intersection at Castroville
Boulevard and Route 156 is the only signal along the route west of
US 101. Because of that, drivers may be unprepared for traffic that has
completely stopped due to a red signal. The accident rate at the
Castroville Boulevard intersection on Route 156 is over twice the
rate of what would be expected of a similar intersection in
California. Additionally, the frequent stoppage of traffic due to the
signal causes congestion. Traffic has been known to back-up in both
directions for miles during the Summer and for weekend events on the
peninsula.
(Source: June 2020 CTC Agenda, Agenda Item
2.5c.(8))
In December 2020, it was reported that the first phase
of the long-awaited Route 156 corridor improvement project was fully
funded and ready for construction after being approved for $20 million in
state gas tax funding by the California Transportation Commission.
According to the Transportation Agency for Monterey County, the state
transportation commission gave the thumbs to allocating SB 1 trade
corridor enhancement program funds for the $55.2 million Castroville
Boulevard interchange project. The funding was part of a $2 billion
package approved for 56 projects across the state aimed at federally
designated trade corridors of national and regional significance with a
“high volume of freight movement” such as Route 156, which
supports the county’s $4.4 billion-per-year agricultural industry by
serving a key route for truck traffic. The state funding means the
Castroville Boulevard interchange project now has the entire $29.5 million
needed to move forward with construction in the next two years. It is part
of the overall $380 million Route 156 improvement project that includes a
proposed $75 million four-lane expressway between the new Castroville
Boulevard interchange and US 101 in Prunedale, and a new $250 million
interchange at Route 156 and US 101. The project includes constructing a
new Castroville Boulevard interchange including an overpass and three
roundabouts to the east of the existing four-way stoplight and expanding
the highway to four lanes from the stoplight intersection to the new
location. It will be constructed to operate in conjunction with both the
current highway route and the proposed four-lane expressway. In addition
to the $20 million in state SB 1 funding, the interchange project is being
funded by about $27.7 million in state Transportation Improvement Program
funding, $5 million in developer fees and $2.25 million in voter-approved
Measure X funding. The project was originally slated to receive $30
million in Measure X funding but Hale said the state funding allowed
Transportation Agency for Monterey County to redirect those funds to the
Blackie Road extension, which would connect Castroville’s industrial
area to the new Castroville Boulevard interchange and allow truck traffic
to avoid Route 183 through downtown Castroville and the interchange at US 101 and Route 183.
(Source: Monterey Herald, 12/3/2020)
In June 2021, it was reported that
this project is one of the projects under consideration for the funds
received from sale of the ROW purchased for the freeway routing of the
Prunedale Bypass, the adoption of which was undone in June 2021. This
project (EA 05-31600, ProjID 0500000497) proposes to remove and
reconstruct the current interchange. The new interchange
configuration will include a fully functioning interchange and a new
flyover structure which will connect eastbound Route 156 traffic to
northbound US 101. This project also proposes to convert US 101 from
a four-lane expressway to a four-lane freeway within the project
limits. This segment of US 101 experiences congestion in both the
northbound and southbound directions on a regular basis, especially on
weekends. Heavy weekend traffic is generated by tourism from the Bay
Area to the Monterey Peninsula and Big Sur. There are safety
concerns and operational deficiencies due to poor weaving distances and
at-grade intersections. The operational deficiencies exacerbate the
congestion problems. The project proposes to improve safety and address
numerous operational deficiencies on US 101 by improving weaving
distances, removing at-grade intersections, and constructing a new
frontage road. Cost Range: $300,000,000 to $425,000,000.
(Source: June 2021 CTC Agenda, Agenda Item
2.3a.(1); June 2021 CTC Agenda, Agenda Item 4.27)
In December 2021, there was an update on the status of
this project: A planned westbound connector at the intersection of Route 156 and US 101 will extend the current onramp an additional 1,800 feet and
will include a ramp meter. Caltrans is conducting preliminary engineering
to determine the size and cost of the project.
(Source: BenitoLink, 12/8/2021)
In May 2023, it was reported that the Transportation
Agency for Monterey County announced that the Route 156/Castroville
Boulevard project is not expected to be ready to list by the June 30 2023
funding deadline. Ready to list means a project has met certain criteria
by the time funding is allocated. The project, which was approved under
Monterey Counties Measure X in 2016, is being held up by PG&E utility
relocation work that will not be completed until December. Now, to make
sure the project avoids losing funding, the California Transportation
Commission is calling for at-risk funding allocation. This funding would
be conditional and would only go through if Caltrans got approval to
develop the land from PG&E. The project has been in the works for more
than a decade. It would get rid of the only traffic light on Route 156 and
replace it with a roundabout. The project was originally expected to cost
$29.5 million, with funding coming from both state and local sources. Now,
that price tag has ballooned by $18 million and is estimated to cost $47.5
million. The TAMC has proposed that the additional funding come from
additional Measure X funds and California's Trade Corridor Enhancement
Program. In their June meeting, the California Transportation Commission
approved an environmental impact report for the project. A 12-month time
extension was also approved to request the $20 million Trade Corridor
Enhancement Program funding. The extension provides time for PG&E to
complete the utility relocation work and for Caltrans to finish
right-of-way certification.
(Source: KSBW, 5/24/2023; KSBW, 7/3/2023)
In June 2023, the CTC had on its agenda the following
project, which was deleted from the agenda before the meeting: 05-Mon-101,
PM 94.6/96.8 05-Mon-156, PM R1.6/T5.2. Route 156 West Corridor.
Widen Route 156 between US 101 and Castroville Boulevard and rebuild the
US 101/Route 156 interchange, in Monterey County. (FEIR Addendum) (PPNO
0057D) (TCEP) (STIP). The project is located on US 101 from postmile
94.6 to postmile 96.8 and SR 156 from postmile R1.6 to postmile T5.2, in
Monterey County. The Department proposes to widen Route 156 from 2 lanes
to 4 lanes and convert US 101 from an expressway to a freeway. The
project is currently programmed in the 2020 State Transportation
Improvement Program (STIP) and Transportation Corridor Enhancement
Program (TCEP) for a total of $13,294,000 which includes Right of Way
(Capital) and Construction (Capital). Construction is estimated to begin
in 2024-25. The scope, as described for the preferred alternative, is
consistent with the project scope as programmed by the Commission in the
2020 STIP/TCEP. A copy of the FEIR has been provided to Commission
staff. The Commission approved the project for future consideration of
funding on August 6, 2013, under Resolution E-13-65. The project has
been divided into three segments and various design modifications have
been made such as shifting the alignment of SR 156 West southward to
accommodate the new design of the grade-separated interchange and the
acquisition of approximately 9.79 acres of additional property. The new
alignment would result in additional impacts to jurisdictional waters
and wetlands. Additionally, after further coordination with CDFW, it was
determined that habitat for California tiger salamander and Santa Cruz
long-toed salamander would be impacted by the project. As a result,
additional avoidance, minimization, and mitigation measures were added
to the project. The Department subsequently completed an Addendum to the
FEIR pursuant to CEQA. The Department has approved this project for
construction. This approval and the Addendum will satisfy the
environmental requirements for this stage of the planning process.
(Source: June 2023 CTC Agenda, Agenda Item 2.2c.(2) Item 4)
From Route 101 to Route 152 passing near San Juan Bautista and Hollister.
In 1963, this segment was defined as "(b) Route 101 near The Rocks to Route 152 via San Juan Bautista and Hollister."
On the 1966 Division of Highways State Map the route of Route 156 west of San Juan Bautista is shown upgraded to a new expressway.
In 1968, Chapter 282 clarified the routing as "(b) Route 101 near
The
Rocks to Route 152 via passing near
San Juan Bautista and Hollister."
This entire routing was LRN 22. The original portion of the route was defined in 1909 and ran from San Juan Bautista to Hollister. In 1919, the portion from Hollister to Route 152 was defined, and in 1933, the remainder of the route (between Castroville and San Juan Bautista) was added. It was signed as Route 156 by 1938 (as it shows up on the 1938 State Highway Map as a state signed route), but was not part of the original 1934 state signage of routes.
Within San Benito County the original path of Legislative Route 22 used
the following route west of Route 152:
(Source: Gribblenation Blog: "California State Route 156")
Within Monterey County LRN 22 westbound multiplexed US 101 southbound
through Prunedale to San Miguel Canyon Road. From San Miguel Canyon Road
LRN 22 turned west onto Castroville Boulevard where it continued onward to
Salinas Street in Castroville. Within Castroville LRN 22 and later Route 156 swung north onto Merritt Street to meet Route 1 at Preston Road. On
the September 1935 Department of Public Works guide the new route of LRN 22 west of San Juan Buatista to US 101/LRN 2 (referred to the Prunedale
Cut-Off) is discussed. The original route of LRN 22 on Rocks Road is
referred to as "a winding county road" that was immediately improved
temporarily with an oiled earth application upon being adopted in 1933.
The new junction with LRN 22 and US 101/LRN 2 is shown to be a
Y-Configuration. Route 156 between Prunedale west to Castroville was
realigned onto the modern two-lane expressway circa 1944. The realignment
of Route 156 between Castroville and Prunedale was built in conjunction
with a realignment of Route 1 through Castroville. Route 156 subsequently
met Route 1 at western terminus along Salinas Street at Merritt Street.
(Source: Gribblenation Blog: "California State Route 156")
LRN 22 used Blackie Road in Prunedale from US 101 to reach LRN 118
(modern Route 183) on Merritt Street in Castroville. This is alignment is
shown on the 1935 California Divisions of Highway Map of Monterey County.
It doesn't appear Blackie Road was part of Route 156 when it was signed
over LRN 22 in 1964 but the state highway map doesn't provide enough
detail to be certain.
(Source: Gribblenation Blog: "California State Route 156")
San Juan Baustista Y (~ SBT 0.0 to SBT 0.082)
The San Juan Grade was the original routing of US 101
in this area. The July 1914 California Highway Bulletin noted surveys for
the San Juan Grade were complete in San Benito County and in Monterey
County, with LRN 2 from the Monterey County Line to San Juan Bautista in
the process of construction as an unpaved road. A contract to
construct LRN 2 in paved Portland Cement north of San Juan Bautista was
awarded on July 6, 1914. The year of 1931 featured the construction
of the Prunedale Cutoff that replaced the San Juan Grade as the new
alignment of US 101/LRN 2. The Prunedale Cutoff alignment of US 101
bypassed San Juan Bautista by way of the communities of Santa Rita,
Prunedale and Dumbarton, and was opened to traffic during the summer of
1932. The San Juan Grade was retained as a spur of LRN 2 east of US 101 on the Prunedale Cutoff. In 1935, planning was on going for a new
route for LRN 22 (future Route 156, which meets US 101) west of San Juan
Bautista to US 101/LRN 2 at the Prunedale Cutoff. This new route would
include a new Y junction (the San Juan Bautista Y). The original
route of LRN 22 on Rocks Road is referred to as "a winding county road"
that was immediately improved temporarily with an oiled earth application
upon being adopted in 1933. The new routing of LRN 22 west of San
Jaun Bautista is noted to negate the need for traffic to use the original
routing of US 101 via the San Juan Grade. The San Juan Bautista Y
was in line for future beautification that would include mission style
walls, a campanile and a cross. The completion of new routing for LRN 22
west of San Juan Bautista led to the relinquishment by 1936 of the San
Juan Grade from the State Highway System. The beautification of the
Y was completed by 1938.
(Source: Gribblenation Blog (Tom Fearer), "Former US Route 101 and California State Route 156 at San Juan Bautista Y", 12/2022)
In 1959, the new San Juan Interchange opened as a
replacement for intersection of US 101/LRN 2 and Route 156/LRN 22 at San
Juan Bautista Y. At the time, the San Juan Bautista Y had the
highest rate of accidents of any state highway segment in San Benito
County. The cross and campanile of San Juan Bautista Y were
preserved so they could be enjoyed by the traveling public.
(Source: Gribblenation Blog (Tom Fearer), "Former US Route 101 and California State Route 156 at San Juan Bautista Y", 12/2022)
US 101 to Hollister (Northern Business Route Terminus)
Route 156 Widening - US 101 to Hollister (SBT 3.0 to R8.2)
In his 2006 Strategic Growth Plan, Governor Schwartzenegger proposed converting two major conventional roadway segments to four-lane expressway. Projects have major safety and mobility benefits for travel from the Bay Area to the Monterey Peninsula and from the Central Valley to US 101.
2007 CMIA. Two projects on Route 156 in Monterey County were submitted to the Corridor Mobility Improvement Account for funding. These projects were a 4 lane expressway, Alameda to Union-Mitchell ($37,987K requested) and the Route 156 Corridor west phase 1 ($166,700K requested) . Neither was recommended for funding.
In November 2007, the CTC reviewed a draft EIR for a project to construct roadway improvements that include widening, from two lanes to four lanes, a portion of Route 156 near Hollister. The project is not fully funded. The project is programmed in the 2006 State Transportation Improvement Program for project development and right-of-way for $22,203,000. The total cost of the project is estimated to be $78,300,000, capital and support. This project should be ready for construction in Fiscal Year 2009-10, depending on the availability of funds. The alternatives are basically (a) whether the roadway is divided or conventional, and (b) whether there are frontage roads, and on which sides of the highway. The project would be between The Alameda (PM 3.0) and San Juan Road (PM 8.2).
In December 2008, the CTC approved for
future consideration of funding a project that would widen the existing
two-lane conventional highway to a four-lane expressway from The Alameda
(PM 3.0) in San Juan Bautista to 0.2 mile east of Fourth Street/Business Route 156 (PM
R8.2). The project is fully funded in the 2008 State Transportation
Improvement Program with Regional Improvement Program , Interregional
Improvement Program, local, and federal funds. The estimated cost of the
project is $69,611,000, capital and support, and is estimated to begin
construction in Fiscal Year 2012-13. Issues with the construction,
permanently removing farmlands and the public controversy associated with
the project resulted in an Environmental Impact Report (EIR) being
completed for this project. Upon completion of the EIR, impacts related to
farmlands are anticipated to be significant and unmitigable. As a result,
a Statement of Overriding Consideration was adopted.
In October 2011, the CTC approved for future consideration of funding a project to widen Route 156 from a two-lane conventional highway to a four-lane expressway on new alignment from the Alameda in San Juan Bautista to just east of Fourth Street. The project is programmed in the 2010 State Transportation Improvement Program and includes local funds. Total estimated project cost is $69,961,000 for capital and support. The scope as described for the preferred alternative is consistent with the project scope programmed by the Commission in the 2010 State Transportation Improvement Program. A copy of the FEIR has been provided to Commission staff. Resources that may be impacted by the project include; noise, biological resources, hydrology and floodplains, and farmlands. Potential impacts associated with the project can all be mitigated to below significance through proposed mitigation measures with the exception of farmlands. The proposed improvements, with all recommended mitigation measures, would still have significant adverse impacts to farmlands in San Benito County with 127 acres of prime farmland being converted to non-agricultural purposes. As a result, a Final Environmental Impact Report was prepared for the project.
In December 2011, it was reported that the Monterey County Transportation Agency is considering funding the new alignment via toll lanes. The plan would be to charge drivers up to $2 to use the new lanes, with the price varying by time of day and traffic conditions. The money would be used to help pay for a project that could cost more than $106 million, of which only $13 million is in hand -- the impact of Monterey County's failure to get two-thirds support for a sales tax increase a few years ago. If the plan moves ahead, construction could start in 2016. If not, it may be 15 to 20 years before a bypass is built. The current route would be turned into a frontage road, one that could be used by residents so they would not have to pay a toll.
In November 2016, it was reported that there are plans
to turn Route 156 into a four-lane expressway in and near San Juan
Bautista to Hollister. Construction on the $44.6 million job should start
in 2019 and take two years.
(Source: Mercury News, 11/3/2016)
The 2018 STIP, approved at the CTC March 2018 meeting, appears to adjust construction funding from $9.639M to $14.7M in FY19-20. The project, PPNO 0297, is in San Juan Bautista, from The Alameda to 0.2 mile east of Fourth Street. Widen to 4 lanes.
The 2020 STIP, approved at the CTC March 2020 meeting,
continues programmed funding of $14,700K for PPNO 0297 "4-lane expressway,
San Juan Bautista (RIP)". It also included PPNO 0297, 4-lane expressway,
San Juan Bautista (IIP), in the Interregional portion of the STIP with no
change in programming: $81,554K in prior year funding.
(Source: March 2020 CTC Agenda, Item 4.7, 2020 STIP
Adopted 3/25/2020)
In November 2020, it was reported that the San Benito
Route 156 Improvement Project will be a five-mile, 4-lane expressway
between The Alameda in San Juan Bautista to the Business Route 156 on Route 156 near
Hollister. The cost of the project will be about $108 million, which is
roughly $30 million less than a previous estimated price tag. The
official construction contract is split up into two phases: utility
relocation and road work. Caltrans won’t break ground until December
2021 but commuters will start seeing construction work at Union and
Mitchell roads beginning in April or May 2021. It will be a two-year
construction timeline with work finalizing in December 2023 until March
2024. All of the work is going to be on a new alignment and the existing
highway will still be functional as a frontage road for farm equipment and
local traffic. To start the project, on Oct. 27, 2020, Caltrans released
the “Ready to List”, which is the first step to sending a
packet out for the advertisement period to look for construction
contractors to review, pick up plans and submit a bid. The history: In
2012, a California Environmental Quality Act document was the subject of a
lawsuit, causing a delay. Caltrans had to go through the court process to
settle things. Then four years later, the California Transportation
Commission at the time didn’t have the funding when Caltrans was
ready for construction, which delayed the project for two more years. For
the last several years the delay has really been related to property
acquisition and utility agreements. This is because they have to come to
an agreement to relocate a variety of different utilities such as San
Benito Water District, PG&E, AT&T, Charter and Comcast. There are
a variety of reasons they discuss including fires, mergers with companies,
layoffs and utilities. Most of the accusations are complete and two of
them in the imminent domain process. The utility companies have quite a
bit of work to do because there’s gas transmission, gas distribution
and electrical transmission that are pretty long runs because
they’re adjacent to the highway.
(Source: San Benito.Com, 11/3/2020)
In December 2020, the CTC approved the following
allocation for State Administered STIP Projects on the State Highway
System: $60,010,000 (RIP/19-20 $15,104,000 Const + IIP/19-20 $11,000,000
Const Sup / $33,906,000 Const) for 05-SBt-156 PM 3.0/R8.2. PPNO 05-0297
ProjID 0500000505 EA 34490. San Benito Route 156 Improvement Project.
Route 156 In San Juan Bautista, from The Alameda to 0.2 mile east of
Fourth Street. Widen to 4 lanes.(CEQA - EIR, 08/15/2011; Re-validation
01/10/2020) (NEPA - FONSI, 08/15/2011; Re-validation 01/10/2020) (Right of
Way Certification: 10/26/2020) (Future consideration of funding approved
under Resolution E-11-76: October 2011)
(Source: December 2020 CTC Agenda, Agenda Item
2.5c.(1) #1)
In June 2021, the CTC approved the following SB1/LPP
allocation: $2,500,000. 05-SBt-156 3.0/R8.2. PPNO 05-0297; ProjID
0500000505; EA 34490. San Benito Route 156 Improvement Project. Route 156
In San Juan Bautista, from The Alameda to 0.2 mile east of Fourth Street.
Widen to 4 lanes. (Future consideration of funding approved under
Resolution E-11-76; October 2011.) This allocation of $2,500,000 in
LPP-Formulaic funds will be used to reduce the local funds to
$7,139,000 for the STIP project approved in December 2020 under
Resolution FP-20-35 . (Concurrent LPP-F Programming Amendment under
Resolution LPP-P-2021-15; June 2021) (The Department requests
non-proportional spending) Allocation: CONST $2,500,000.
(Source: June 2021 CTC Agenda, Agenda Item 2.5s.(1)
#1)
Also in June 2021, the CTC approved a request from the
Council of San Benito County Governments to add the following to their
2019 LLP-Formulaic fund allocation. The State Route 156 Improvement
Project and program $2,500,000 to construction in Fiscal Year 2020-21.
This project will convert five miles of a two-lane conventional highway
into a four-lane at-grade expressway from The Alameda in San Juan Bautista
to Business Route 156 near Hollister. The anticipated benefits of this project include
improving route continuity, reducing congestion, and increasing safety.
(Source: June 2021 CTC Agenda, Agenda Item 4.16)
In December 2021, there was an update on the status of
this project: A $60 million plan to construct a four-lane expressway on
Highway 156 from San Juan Bautista to Hollister is the largest of the
current projects. Construction was originally estimated to begin in the
summer of 2021, but preparatory work is still being done in the area.
Drabinski said work by PG&E to relocate utilities in advance of the
project should conclude by the end of this month. Details for prospective
bidders will be announced in January with work to commence when the job is
awarded.
(Source: BenitoLink, 12/8/2021)
In May 2022, the CTC approved a request for an
additional $14,732,000 in Construction Capital for the STIP Roadway
Widening project on Route 156, in San Benito County (05-SBt-156 3.0/R8.2.
PPNO 05-0297; ProjID 0500000505; EA 34490), to award the construction
contract. This project is located on Route 156 in the City of San Juan
Bautista and Hollister, from The Alameda to east of Fourth Street, in San
Benito County. The project will convert the two-lane conventional
highway into a four-lane expressway. In April 2018, the project was
programmed for $47,700,000 in Construction Capital in the STIP,
$33,000,000 from the Interregional Improvement Program (IIP) and
$14,700,000 from the Regional Improvement Program (RIP), for allocation in
Fiscal Year 2019-20. In June 2020, the project received a 20-month
allocation time extension for construction. In December 2020, the
project was allocated for $49,010,000 in Construction Capital in the STIP,
$33,906,000 from the IIP and $15,104,000 from the RIP. In June 2021, the
project was allocated for $2,500,000 in Construction Capital in the Local
Partnership Program. The total allocated amount is $51,510,000 in
Construction Capital. In January 2022, the project received a
nine-month award time extension for the STIP funds. Bids were
opened in March 2022, and the amount required to award to the lowest
bidder exceeded the amount available from project allocated funds.
In January 2022, the Department advertised the contract and held bid
opening in March 2022. The contract received six bids, of which, the
lowest bid was 30.3 percent above the Engineer’s Estimate
(EE). The five remaining bids ranged in costs form 30.6 percent to
44.7 percent over the EE. The EE was based on historical unit prices
at the time it was completed in December 2021. The Department
anticipated that the recent COVID-19 pandemic and volatile supply chain
pricing may result in a higher bid, but the full extent of price
difference between the EE’s unit prices and the low bidder’s
unit prices was not anticipated.
(Source: May 2022 CTC Agenda, Agenda Item 2.5e.(6))
In August 2022, it was reported that the San Benito
Route 156 Improvement Project, which adds five new miles of four-lane
expressway along Route 156 between The Alameda in San Juan Bautista and
Hollister, would begin construction on Aug. 22, 2022. Construction is not
predicted to cause additional traffic for drivers who currently use the
highway. The vast majority of the work takes place parallel to the current
roadway and so it will not have substantial impacts on the traveling
public on the existing Route 156.
(Source: Benito Link, 8/18/2022)
In June 2023, the CTC approved for future consideration of funding
05-SBt-156, PM 3.0/R8.2. San Benito Route 156 Improvement Project.
Widen Route 156 from two lanes to four lanes, in San Benito County. (FEIR
Addendum) (PPNO 0297) (STIP). The project is located on Route 156 from
postmile 3.0 to postmile R8.2, in San Benito County. The Department
proposes to widen Route 156 from two lanes to four lanes. The project is
currently programmed in the 2020 STIP for a total of $122,339,000, which
includes Right of Way (Support and Capital) and Construction (Support and
Capital). Construction began in 2022-23. The scope, as described for the
preferred alternative, is consistent with the project scope as programmed
by the Commission in the 2020 STIP. A copy of the FEIR has been provided
to Commission staff. The Commission approved the project for future
consideration of funding on October 27, 2001, under Resolution E-11-76.
Since the approval of the FEIR, several design modifications have been
made. These modifications include, but are not limited to, the addition of
a roundabout, the addition of a lane east of Fourth Street intersection to
have two westbound through lanes of traffic at the intersection of Route 156 and Fourth Street/Business Route 156, eliminating the connection of San Juan
Hollister Road to Union Road by terminating San Juan Hollister Road with a
cul-de-sac, adding a median High-Tension Cable Barrier (HTBC), adding a
concrete barrier, and eliminating retaining wall No. 30. Additionally,
tree trimming was added to the scope of work to provide clearance for
heavy equipment to construct the sound wall. The Department subsequently
completed Addendums to the FEIR pursuant to CEQA. The Department has
approved this project for construction. This approval and the Addendums
will satisfy the environmental requirements for this stage of the planning
process.
(Source: June 2023 CTC Agenda, Agenda Item 2.2c.(2) Item 5)
In June 2023, it was reported that because of the
exceptionally wet 2022-23 rainy season, costs for the Route 156
Improvement Project have increased $13.8 million. Of that amount, the
share paid by the Council of San Benito County Governments (COG), the
regional transportation agency, will increase by $4.25 million.
COG’s original share was going to be about $25 million. According to
Caltrans, the rain storms experienced in the area between January and
March left high levels of groundwater. To continue work it required the
lime treatment. The winter storms also resulted in a new construction
process that involved using more trucks and equipment to integrate the
lime treatment into the project than was suggested by the project’s
geotechnical design report. The Route 156 improvement project adds five
new miles of four-lane expressway along Route 156 between The Alameda in
San Juan Bautista and Hollister, and is expected to conclude in Summer
2025.
(Source: BenitoLink, 6/28/2023)
In June 2023, the CTC approved an additional
$13,808,000 in Construction Capital for the STIP San Benito Route 156
Improvement Project on Route 156, in San Benito County, to complete the
construction contract. This project (05-SBt-156 3/R8.2, PPNO 05-0297,
ProjID 0500000505, EA 34490) is located on Route 156, in the City of San
Juan Bautista and Hollister, from The Alameda to east of Fourth Street, in
San Benito County. The project will convert the two-lane
conventional highway into a four-lane expressway. In April 2018, the
project was programmed for $47,700,000 in Construction Capital in the STIP
($33,000,000 from the Interregional Improvement Program (IIP) and
$14,700,000 from the Regional Improvement Program (RIP)); for allocation
in Fiscal Year 2019-20. In June 2020, the project received a
20-month allocation time extension for construction. In December
2020, the project was allocated for $49,010,000 in Construction Capital in
the STIP ($33,906,000 from the IIP and $15,104,000 from the RIP). In
June 2021, $2,500,000 in Construction Capital from the Senate Bill 1 Local
Partnership Program (Formulaic) was programmed and allocated to the
project. The original total allocated amount is $51,510,000 in
Construction Capital. In January 2022, the project received a
nine-month award time extension for the STIP funds. In May 2022, the
project received supplemental funds in the amount of $14,732,000 in
Construction Capital in the STIP ($10,192,000 from the IIP and $4,540,000
from the RIP); to award the construction contract. In June 2022, the
project was awarded for $63,742,000 in Construction Capital in the STIP
($44,098,000 from the IIP and $19,644,000 from the RIP). In August 2022,
construction began with 490 working days. The remaining funds are
currently at $56,666,000 in Construction Capital. The project is 10
percent complete with 450 working days remaining. The planned
Construction Contract Acceptance is scheduled for May 2025. The Department
is requesting supplemental funds in the amount of $13,808,000 ($9,553,000
from the IIP and $4,255,000 from the RIP) to complete the construction
contract. Total revised amount $77,549,200.
(Source: June 2023 CTC Agenda, Agenda Item 2.5e.(3))
The project realized cost increases due to
differing site conditions relating to unstable soil that was further
destabilized as a result of severe winter storms and high groundwater
level. It has resulted in a higher cost of planned work which will be
addressed through contract change orders. The project will convert a
5-mile segment of a two-lane conventional highway into a four-lane
expressway. As part of building the new lanes, the contract included
construction detail plans and standard special provisions to remove and
recompact the top three feet of the existing ground to ensure a solid
foundation (subgrade) for the embankment construction. If
recompacting the top three feet of soil did not work, the Geotechnical
report included the recommendation to use crushed rock and geotechnical
fabric to strengthen the soil. The contractor bid the project
expecting to follow the plans and provisions by utilizing appropriate
equipment to remove and recompact the soil. However, due to the severity
of Winter storms and high groundwater level, the contractor encountered
unstable soil within a 1.5-mile segment of the project, which hindered the
removal and recompaction of the soil. Upon review of the other
options to stabilize the soil, geotechnical design recommended to process
the top 18 inches of soil with lime treatment to stabilize the
existing ground. If there are areas of failure after the lime
treatment, the contractor would process the top three feet of soil with
lime treatment. The cost to lime treat the existing ground will
amount to $3,421,000. This has also resulted in a change in the
character of work as the contractor will have to use other equipment and
conventional trucking to haul the soil to a specific area of the project
limits for lime treatment. The cost for the change in
construction method will amount to $10,387,000.
(Source: June 2023 CTC Agenda, Agenda Item 2.5e.(3))
In 1997, a bypass was opened from a point west of town near Union Road to the intersection of Route 156 and San Felipe Road angling bypassing the city of Hollister (~ SBT R7.811 to SBT R13.245). This is a two-lane bypass built to expressway standards. The old routing through town is still signed as Route 156 and Route 25 for some of it. There are plans to widen this to four lanes; the EIR was completed in September 2002, per CTC September 2002 Agenda.
In August 2010, the CTC approved relinquishment of right of way in the city of Hollister on Route 156U (San Juan Road, Business Route 156), being the city’s portion of the San Benito River Bridge (SBT R008.45), consisting of superseded highway right of way.
In February 2010, the CTC approved relinquishment of right of way in the county of San Benito along Route 156U at the San Benito River Bridge (SBT R008.45) , consisting of superseded highway right of way, and along Route 156 at Buena Vista Road, consisting of collateral facilities.
Constructed to freeway standards from US 101 near San Juan Bautista to San Juan Road.
Route 25 / Route 156 Roundabout (~ SBT R11.256)
In August 2018, it was reported that Caltrans plans to build a roundabout at the intersection
of Route 25 and Route 156, scheduled for completion in August 2021. It
will eventually get replaced by an interchange when the Route 25 expansion
project moves forward at an undetermined time. The roundabout project with
a $7.7 million construction cost, to go with $3 million in “support
costs”, will be funded by the state as a safety improvement project
through the State Highway Operations and Protection Program, or SHOPP. The
project remains in initial planning stages. There is “concept
layout” and it is heading into the design and then construction
phases, said roundabout Project Manager Brandy Rider. Plans presented to
the local COG board in recent months show Caltrans will be ready to list
the roundabout project for bidding in late August 2020, and it is set for
a target end construction date at the end of October 2021. The roundabout
is separate, however, from the Route 25 expansion. The timing and
financing of that will depend on whether San Benito County taxpayers
approve a 30-year, 1 percent sales tax on the November ballot. Under
long-term Route 25 expansion plans, the roundabout would be replaced by an
interchange. That replacement would happen many years down the road, and
Rider said it could be 15 years or so until such a change might occur.
While Caltrans is paying for the roundabout, the state has made it clear
local taxpayers would have to cover the majority of the expansion funding,
which would come from the ballot measure if approved. The nearly $300
million expansion would result in a four-lane, 11.2-mile commuter highway
from Hollister to Santa Clara County.
(Source: San Benito Live, 8/15/2018)
In August 2018, the CTC amended the SHOPP to add the
following project: 05-SBt-25 54.0 PPNO 2746, Project 0517000185, EA 1J480.
Route 25 Near Hollister, at the intersection of Route 25 and Route 156.
Improve safety by constructing a roundabout. Est. cost: $10,628,000. Est.
construction start: 10/28/2021.
(Source: August 2018 CTC Agenda Item 2.1a.(1))
In June 2019, it was reported that Caltrans District 5
will hold a public information meeting/open house about a proposed safety
roundabout project for the intersection of Route 25 and Route 156.
(Source: BenitoLink, 6/20/2019)
In December 2019, it was reported that the roundabout
planned for the Route 25/Route 156 intersection at Hollister’s north
end is moving forward and is on schedule. According to Caltrans, the
project is fully funded, its environmental review is completed and final
designs and right-of-way acquisitions are scheduled for August 2020. The
$10.7 million project aims to make the busy intersection safer.
Roundabouts are increasingly common in new residential developments, as a
substitute for four-way stops. The state has begun using them at busy
traffic-signaled intersections that have had high accident rates. New,
successful roundabout projects in Tracy and Palmdale match
Hollister’s traffic patterns, according to the state. The plan is a
short-term fix, however, as the state’s long-term vision is to
realign and widen Route 25 to four lanes and build an interchange at its
connection to Route 156. No date or funding has been set for that new
highway replacement for the jammed two-lane commuter route that Route 25
has become. The proposal to place an interchange at this location will not
be finalized, under best case scenarios, until 2028, according to
Caltrans. Construction on the roundabout could start as early as the
summer of 2021 with a winter 2021 completion date. The roundabout is a
2-lane design, and state planners said it will be able to handle big rigs.
(Source: San Benito.Com, 12/20/2019)
The 2020 SHOPP, approved in May 2020, included the
following Collision Reduction item of interest (carried over from the 2018
SHOPP): 05-San Benito-25 PM 54.0 PPNO 2746 Proj ID 0517000185 EA 1J480.
Route 25 Near Hollister, at the intersection of Route 25 and Route 156.
Improve safety by constructing a roundabout. Programmed in FY20-21, with
construction scheduled to start in June 2021. Total project cost is
$10,628K, with $7,663K being capital (const and right of way) and $2,965K
being support (engineering, environmental, etc.).
(Source: 2020 Approved SHOPP a/o May 2020)
In August 2021, the CTC approved the following SHOPP
amendment: 05-SBt-25 54.0 53.7/54.03 PPNO 05-2746;
ProjID 0517000185; EA 1J480. Route 25 Near Hollister, at the intersection
of Route 25 and Route 156. Improve safety by constructing a
roundabout. (Concurrent CONST and CON ENG allocation under Resolution
FP-21-12; August 2021.) Note: Split off environmental mitigation project
EA 1J481/PPNO 05-2746Y for landscape and monitoring work from parent
project EA 1J480/PPNO 05-2746. Updated financials: ($ × 1,000): Const
Cap $7,659 ⇒ $6,559; Total $10,628 ⇒ $9,528.
(Source: August 2021 CTC Agenda, Agenda Item
2.1a.(1d) #5)
Also in August 2021, the CTC approved an allocation
request for $12,022,000 for the State Highway Operation and Protection
Program (SHOPP) Safety Improvements project, on Route 25 in San Benito
County, to advertise the project. This request exceeds the programmed
amount by over 20%. This project is located on Route 25 near Hollister, at
the intersection of Route 25 and Route 156, in San Benito County. The
signalized intersection of Route 25 and Route 156 in San Benito County is
experiencing a pattern of broadside and rear end collisions, due to a
recurrence of red light runs. The purpose of this project is to improve
the intersection of Route 25/Route 156 by reducing the number and severity
of collisions. The project proposes to construct a roundabout at
this intersection with key features that include replacing the
intersection with a multi-lane roundabout which will minimize excessive
queuing and delay. The roundabout will operate under capacity, have
adequate queue storage, and be adequately sized to handle a truck
tractor-semitrailer. This project was originally programmed in 2018 for
$7,659,000 in construction capital and $1,455,000 in construction support
with construction in Fiscal Year 2020-21. The project also includes
landscape mitigation and plant establishment elements. A SHOPP
Technical Amendment is being requested concurrently, with this allocation
request, at the August 2021 Commission meeting to move the landscape
mitigation and plant establishment work to a child project (EA
05-1J481/PPNO 2746Y) for delivery in 2023-24, due to the three-year
establishment period. The child landscape project’s construction
capital and support will be funded with $1,100,000 from the parent
project’s construction capital. The updated Engineer’s
Estimate (EE) includes State furnished materials, mobilization, and
contingency for construction capital of $9,857,000; which is 50.3 percent
over the $6,559,000 remaining programmed amount after moving the landscape
mitigation and plant establishment elements. The updated
construction support estimate is $2,165,000; which is 48.8 percent over
the programmed amount. The project has an approved time extension
for allocation through August 2021. Pending the approval of this
request, the Department plans to advertise the project contract in
September 2021 and begin construction in February 2022. Construction
is planned for two seasons with 210 working days and completion by January
2023.
(Source: August 2021 CTC Agenda, Agenda Item
2.5d.(3))
The Department received extensive public input on this
project regarding truck movements and sought a peer review from an
external roundabout consultant. The peer review was conducted in
September 2020 and the findings centered on the design of the multi-lane
roundabout and how to best serve the high truck volumes. Based on the
public comments received, the design configuration was revised to reflect
an innovative turbo roundabout layout with raised lane dividers, to better
mitigate the potential for low-speed merging conflicts due to the acute
intersection angle of Route 25 and Route 156. Due to the restrictions
associated with the new turbo configuration and raised lane dividers,
overhead sign structures are needed on each of the four entries to aid
drivers in selecting the appropriate lane pertaining to their desired
destination. This is a departure from the standard wood-post signage
originally called out for in the project. Also, the diameter of the
circulatory roadway needs to be enlarged by 30 percent and the structural
section increased to adequately accommodate the volume of large vehicles
which regularly traverse the intersection. According to a Caltrans
spokesperson, the roundabout planned at that intersection will be the
first of its kind in California. The design known as a turbo roundabout is
240 feet in diameter, includes raised dividers to keep motorists from
changing lanes, and uses overhead and road markings for navigation.
Construction is expected to begin in January, pending weather conditions.
The overhead lane markings will note which lane leads to either Route 25
or Route 156, will be placed about 350 feet from the roundabout. The
intersection became a high priority for Caltrans because it has almost
double the average rate of collisions. According to Caltrans, there were
126 collisions between 2009 and 2018 with two fatalities. Caltrans will be
working on an easy-to-understand design they intend to present at public
hearings in the future. This is because the engineer’s design may be
difficult for the public to understand as it contains a lot more
information than just the drawings of the lanes. The roundabout design is
similar to one being constructed in Jacksonville, Florida. The turbo
roundabout was recently invented in the Netherlands. Its key feature is
that it prevents drivers from changing lanes, thus reducing rates of
roundabout collisions. Caltrans did not have to deal with property
acquisition for this project as it stayed within the existing
right-of-way. Additionally, the overpass that is planned at that
intersection as part of the Route 25 widening project will not be
constructed over the roundabout. Instead, Caltrans is working on designs
that may incorporate aspects of the roundabout to the overpass, which
would save money along the way.
(Source: August 2021 CTC Agenda, Agenda Item
2.5d.(3); BenitoLink, 8/30/2021)
The latest Engineering Estimate for the cost reflects
the current unit prices for projects going out to bid in the region and
shows the increase of $3,298,000. The increase is primarily driven
by the increase in hot mix asphalt (11,000 tons to 19,500 tons), four
overhead sign structures, additional temporary traffic controls, and
additional roadway excavation. In addition, the original roundabout
design included a center island with planting and a one- year plant
establishment to be included with the road project. During final
reviews, Department maintenance staff requested that all planting be
eliminated from the center island, due to safety concerns and the
long-term maintenance of vegetation within the center island. The
design changes due to the removal of the center island planting resulted
in the need to re-evaluate the Visual Impact Analysis. The
re-evaluation recommended landscaping be placed outside the roundabout to
mitigate for additional signs structures and the lighting features as
required by the new design. This resulted in the need for a split off
landscape project to accommodate the new planting plan and a three-year
plant establishment period at a cost of $1,100,000. A construction support
cost increase of 48.8 percent is also needed due to an increase of working
days, from 130 to 210, and the complicated turbo roundabout design staging
needed during construction. Additionally, on-going coordination with the
local community identified the need for greater outreach to the community
and a public awareness campaign during construction.
(Source: August 2021 CTC Agenda, Agenda Item
2.5d.(3))
In December 2021, there was an update on the status of
this project: The roundabout is planned for the intersection of Route 25
and Route 156, north of Hollister. Bidding was opened on Oct. 27 with the
contract for the $10.7 million project awarded to GraniteRock
Construction, according to Caltrans Public Information Officer Kevin
Drabinski. Construction is scheduled to begin in February 2022.
(Source: BenitoLink, 12/8/2021)
In May 2022, construction began on Route 25/Route 156
roundabout. The initial phase of construction will result in lane closures
on the approach to the north Hollister intersection, from westbound Route 156 and southbound Route 25. The project is expected to be completed in
April 2023. The roundabout is planned as an interim solution. An
interchange at Route 25/Route 156 is the long-range improvement planned as
part of the larger Route 25 Expressway Conversion Project. The Measure
G-funded project to widen Route 25 (to be completed over the coming years)
will also include a permanent interchange at this intersection. The
roundabout is a critical safety project designed to hasten the reduction
of the number and severity of collisions at this intersection. The
Caltrans State Highway Operation and Protection Program, which funds
safety projects, identified the need to address immediate safety at this
location. In the interim, Caltrans is addressing this safety need until
the long-range plan for an interchange can be implemented. Although the
proposed roundabout is located at the junction of two high-speed rural
routes, the roundabout design will emphasize speed control. Design
features will control the speed at which vehicles enter, navigate, and
exit the roundabout. Lower vehicle speeds provide more time for entering
drivers to judge, adjust speed for, and enter a gap in circulating
traffic, allowing for safer merges while reducing the frequency and
severity of collisions. The roundabout is a two-lane design and
anticipates truck volumes for the intersection today and into the future.
In accommodating the sweep of truck trailer wheels, a mountable truck
apron is featured around the inside of the roundabout.
(Source: San Benito County on FB, 5/31/2022)
In August 2023, it was reported that the next stage of
construction of the roundabout project project at Route 25 and Route 156,
crews will implement a new, temporary traffic configuration that will
operate similar to a one-lane roundabout. The configuration will remain in
place through the end of the project’s construction in early 2024.
During construction, as vehicles approach, they will be required to slow
down and yield to traffic already in the roundabout before entering. There
will be no signalized traffic lights in place, and travelers will see new
yield signage and other alerts to advise of the upcoming intersection
change. One week before the one-lane roundabout is implemented,
Caltrans will place electronic message signs to alert motorists of the
upcoming configuration change. Speed limits within the project area remain
reduced to 35 mph. This temporary traffic configuration is necessary to
allow crews to complete final work inside the middle of the intersection
for the future “Turbo Roundabout.” When complete, the
roundabout project will be designed to reduce the number and severity of
collisions at the intersection of Route 25 and Route 156. The project will
cost about $14.6 million.
(Source: SanBenito.Com, 8/8/2023)
Hollister (Northern Business Route Terminus) to Route 152
Route 152 / Route 156 Interchange
The SAFETEA-LU act, enacted in August 2005 as the reauthorization of TEA-21, provided the following expenditures on or near this route:
According to vta.org, there are currently plans to build a flyover ramp intersection with Route 152. Estimated completion date is 2008. It opened for public traffic in late January 2009.
The 5-mile portion of Route 156 from US 101 to Route 25 (~ SBT 0.055 to SBT R11.322)is named
the "CAL-FIRE Firefighter Matt Will Memorial Highway". This segment
was named in memory of California Department of Forestry and Fire
Protection (CAL-FIRE) Heavy Fire Equipment Operator (HFEO) Fire Captain
Matt Will, who passed away in the line of duty on October 9, 2007, at the
age of 30, while battling a fire in Monterey County. Matt Will was born in
El Cajon, California on March 13, 1977, and was raised in Campo,
California. He attended elementary through high school in Campo where he
participated in many sports including football, baseball, and wrestling.
He enjoyed many outdoor activities, such as camping, fishing, hunting, and
off-roading. After graduating from high school, Matt Will helped run his
family business where he became proficient at operating heavy equipment.
HFEO Gary Will, father of Matt Will, is employed by CAL-FIRE. Matt Will
followed in his father's footsteps as he pursued the career of his dreams
as a HFEO by applying his passions for heavy equipment and firefighting.
He was always charismatic and caring, and his drive and motivation were
displayed daily. Matt Will's leadership skills carried him to reach his
goals and to encourage others to reach theirs. Matt Will was extremely
knowledgeable, with abundant experience and excellent judgment that
enabled him to be on the fireline operating alone. On October 8, 2007,
HFEO Matt Will tried to get another bulldozer out of a precarious
situation, placing Matt Will in a very dangerous location. The ground of
the steep terrain gave way causing Matt Will's bulldozer to roll 154 feet
down a steep drainage, in which Matt Will sustained injuries. On October
9, Matt Will succumbed to those injuries. Named by Assembly Concurrant
Resolution (ACR) 106, 6/17/2010, Resolution Chapter 38.
(Image sources: Wild Land Firefighting Always Remember, National Fallen Firefighters Assn)
Bridge 43-0044, the San Benito River Bridge, in San Benito County (SBT R008.45) is named the "Ed Hanna Memorial Bridge". It was named by Senate Concurrent Resolution 22, Chapter 65 in 1997. Ed Hanna was a long time San Benito County employee, having worked in the 1940's as county surveyor and later as County Engineer and Road Commissioner.
The flyover ramp at the interchange of Route 152 and Route 156 is named the "Joseph A. Zanger Memorial
Flyover" (~ SCL 0.475). This segment was named in honor of Joseph A.
Zanger, who was born on December 28, 1927, in San Jose, California. After
attending college, Joseph moved to the Pacheco Pass area to help manage
his family's orchard operations. In 1943, the Zanger family founded Casa
de Fruta to complement its farming business. The Casa de Fruta business
started with a small cherry stand built in 1943 and grew to include a
large fruit stand, a restaurant, a park for recreational vehicles, a
lodge, wine tasting, a gift shop, a barnyard zoo, a candy store, a service
station, and a dried fruit mail order business. Joseph studied safety and
economic issues related to the transportation system of central California
and served as an advocate for the improvement of transportation in that
area. In 1978, Joseph served on the planning committee for the I-5 project
from Stockton to Santa Nella/Route 152. In 2005, Joseph also worked to
establish a new route from Route 152/Route 156 to US 101. Joseph's
advocacy for safety and transportation improvements has affected thousands
of motorists. Named by Senate Concurrent Resolution (SCR) 85, Resolution
Chapter 67, on 8/4/2010.
(Image source: Gilroy Dispatch)
The old routing through the city of Hollister is signed as Business Route 156.
This route is part of the De Anza National Historic Trail.
[SHC 253.1] Entire route. Added to the Freeway and Expressway system in 1959.
[SHC 263.1] Entire route.
Overall statistics for Route 156:
In 1933, Chapter 767 defined the route from "[LRN 60] near Topanga Beach to Montalvo-San Fernando Road near Chatsworth" as a state highway. In 1935, this route was added to the highway code as LRN 156, with the definition:
In 1959, Chapter 1062 clarified the definition to be: "[LRN 60] near Topanga Beach but north of the intersection of Sunset Boulevard and [LRN 60] to [LRN 9] at or near Chatsworth"
This is present-day Route 27 (Topanga Canyon). At one time, it was proposed for the Reseda Freeway.
© 1996-2020 Daniel P. Faigin.
Maintained by: Daniel P. Faigin
<webmaster@cahighways.org>.